Zurich Main Street Construction

The Zurich Main Street and Water Project is a shared effort between Huron County and The Municipality of Bluewater. Construction is set to start in early June 2022 and is expected to finish by mid-November 2022. The County of Huron’s scope of work includes the road work (paving and culvert replacement), minor storm sewer and curb repairs. The Municipality’s scope of work includes installing new watermain and replacing sidewalks in the core area. New sidewalk and boulevards will be extended on the north side of Zurich Hensall Road to East Street.


To sign-up for updates and to find more information at:


153 views0 comments

Recent Posts

See All

Short Term Rentals

Council adopted By-law 68-2023 to license, regulate and govern the operation of short-term rentals on June 19th, 2023. The application...